P takes twice as long as Q or three times as long as R to complete a task. If they work together, they can complete the task in two days. How long will it take Q to complete the task on his own?

(SSC CGL Tier-1 2023 (24 Jul · Shift 1 · 9:00 AM))
  1. 8 days
  2. 6 days
  3. 5 days
  4. 7 days
Answer (Detailed Solution Below)
Option 2 : 6 days

Detailed Solution

Concept approach

Time P : Q : R = 6 : 3 : 2

⇒ eff 1 : 2 : 3 = 6 units/day

⇒ work = 12

⇒ Q = 12/2 = 6 days

Ultra Calci trickefficiency units

Times P : Q : R = 6 : 3 : 2 → efficiency 1 : 2 : 3 → 6 per day

work = 6 × 2 = 12 → Q = 12/2 = 6 days

⇒ 6 days