If 90 men can do a certain job in 16 days working 12 hours/day, then find the part of that work which can be completed by 70 men in 24 days working 8 hours/day.

  1. 5/8
  2. 2/3
  3. 1/3
  4. 7/9
Answer (Detailed Solution Below)
Option 4 : 7/9

Detailed Solution

Concept approach

Part = (70 × 24 × 8)/(90 × 16 × 12) = 13440/17280 = 7/9

Ultra Calci trickmultiple of 7 (numerator)

Part = (70 × 24 × 8)/(90 × 16 × 12) → 7 from 70 stays on top, no 7 below

5/8 ✗ 2/3 ✗ 1/3 ✗

⇒ 7/9 ✓ (13440/17280)