R, S and T can finish a work in 20, 15 and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?

(SSC CGL Tier-1 2023 (24 Jul · Shift 4 · 5:15 PM))
  1. 61/7
  2. 50/7
  3. 52/7
  4. 57/8
Answer (Detailed Solution Below)
Option 3 : 52/7

Detailed Solution

Concept approach

LCM 60: R = 3, S = 4, T = 6. 2 days = (3 + 6) + (3 + 4) = 16

⇒ 6 days = 48

⇒ day 7: 9

⇒ 57, left 3

⇒ day 8: 3/7 day

⇒ 7 3/7 = 52/7 days