A, B, C and D can complete a work individually in 20 days, 25 days, 40 days and 50 days, respectively. All four work together for 2 days. Then A, B and C continue for 3 more days. Next A and B work for 4 days. Finally C returns at 150% of his original efficiency and D returns at twice his original efficiency; C and D together finish the remaining work. If ₹31,000 is divided according to actual work done, what is C's share?

(SSC CGL 2026 (24 Oct, Shift 1))
  1. ₹3,950
  2. ₹4,100
  3. ₹4,250
  4. ₹4,400
Answer (Detailed Solution Below)
Option 3 : ₹4,250

Detailed Solution

Concept approach

LCM 200: A 10, B 8, C 5, D 4 per day. Work: all 4 × 2 days = 54; A,B,C 3 days = 69; A,B 4 days = 72

⇒ done 195, left 5. C (7.5) + D (8) = 15.5/day

⇒ 10/31 day. C's work = 10 + 15 + 7.5×10/31 = 850/31. Share = 850/31 ÷ 200 × 31000 = ₹4,250.