Selection KeySelection KeyFree Mock Test
View this question in:

A, B and C working together completed a job in 10 days. However, C only worked for the first three days, when 37/100 of the job was done. Also, the work done by A in 5 days is equal to the work done by B in 4 days. How many days would be required by the fastest worker to complete the entire work?

  1. 25 days
  2. 20 days
  3. 30 days
  4. 40 days
Answer (Detailed Solution Below)
Option 2 : 20 days

Detailed Solution

Concept approach

3(a+b+c) = 0.37 and 10(a+b) + 3c = 1

⇒ 7(a+b) = 0.63

⇒ a+b = 0.09; 5a = 4b

⇒ a = 0.04, b = 0.05; c = 0.0333. Fastest = B

⇒ 20 days