15 men complete a work in 10 days. 15 women complete the same work in 12 days. If all these men and women work together, then the number of days required to complete that work is:

(SSC CGL Tier-1 2023 (26 Jul · Shift 4 · 5:15 PM))
  1. 5⁵⁄₁₁
  2. 4³⁄₁₁
  3. 7²⁄₁₁
  4. 6⁴⁄₁₁
Answer (Detailed Solution Below)
Option 1 : 5⁵⁄₁₁

Detailed Solution

Concept approach

LCM(10, 12) = 60

⇒ men = 6, women = 5 per day

⇒ together 11

⇒ 60/11 = 5 5/11 days

Ultra Calci trickefficiency units

15M × 10 = 15W × 12 → M : W = 6 : 5 → work = 15 × 6 × 10 = 900

all together 90 + 75 = 165 per day → 900/165 = 5 5/11

⇒ 5⁵⁄₁₁