A can complete a work in 20 days and B in 25 days. Both worked together for 10 days and then C alone completed the remaining work in 10 days. In how many days will A, B and C together complete the same work?

(SSC CHSL 05.08.2021 (Shift-1))
  1. 10 days
  2. 5 days
  3. 12 days
  4. 8 days
Answer (Detailed Solution Below)
Option 1 : 10 days

Detailed Solution

Concept approach

10 days: 50% + 40% = 90%

⇒ C does 10% in 10 days (1% per day)

⇒ A + B + C = 5% + 4% + 1% = 10% per day

⇒ 10 days