A and B can do a work in 20 and 30 days respectively. They start the work together and work for 7 days, then both leave and C completes the remaining work in 10 days. How much time will C take to do the whole work?

  1. 20 days
  2. 24 days
  3. 25 days
  4. 30 days
Answer (Detailed Solution Below)
Option 2 : 24 days

Detailed Solution

Concept approach

Total = 60; A 3, B 2

⇒ 7 days = 35

⇒ C does 25 in 10 days

⇒ C = 2.5

⇒ 60/2.5 = 24 days

Ultra Calci trickmultiple-of-12

A + B for 7 days = 7 × (1/20 + 1/30) = 7/12

⇒ C does the remaining 5/12 in 10 days

C alone = 10 × 12/5 = 2 × 12 → multiple of 12

20 ✗ 25 ✗ 30 ✗ 24 ✓

⇒ 24 days