A can do a piece of work in 8 days, while B can do it in 18 days. In how many days will the work be completed if they both work on alternate days starting with B?

(SSC CGL Tier-1 2023 (21 Jul · Shift 4 · 5:15 PM))
  1. 11⅓
  2. 12⅓
  3. 10
  4. 10⅓
Answer (Detailed Solution Below)
Option 1 : 11⅓

Detailed Solution

Concept approach

LCM 72

⇒ A = 9, B = 4

⇒ 2 days = 13

⇒ 10 days = 65

⇒ left 7: day 11 (B) 4

⇒ left 3

⇒ A 3/9 = 1/3 day

⇒ 11⅓ days