A and B can do a project in 9 days. B and C can do it in 12 days while C and A can do it in 18 days. In how many days A, B and C all working together, can finish the project?

(SSC CGL Tier-1 2023 (20 Jul · Shift 3 · 2:30 PM))
  1. 9
  2. 8
  3. 11
  4. 10
Answer (Detailed Solution Below)
Option 2 : 8

Detailed Solution

Concept approach

LCM 36

⇒ A+B = 4, B+C = 3, C+A = 2

⇒ 2(A+B+C) = 9

⇒ A+B+C = 4.5

⇒ 36/4.5 = 8 days

Ultra Calci trickLCM work

LCM 36 → A + B = 4, B + C = 3, C + A = 2 → 2 × all = 9 → 4.5 per day

36/4.5 = 8 days

⇒ 8