P and Q can complete a project in 15 days and 10 days, respectively. They started doing the work together, but after 2 days, Q had to leave and P alone completed the remaining work. In how many days was the whole work completed?

(SSC CGL Tier-1 2022 (1 Dec · Shift 1 · 9:00 AM))
  1. 11
  2. 12
  3. 13
  4. 10
Answer (Detailed Solution Below)
Option 2 : 12

Detailed Solution

Concept approach

Together 2 days: 2 × (1/15 + 1/10) = 1/3 ; left 2/3 by P

⇒ 2/3 × 15 = 10 days

⇒ total 2 + 10 = 12 days