Selection KeySelection KeyFree Mock Test
View this question in:

20 women and 15 men together can complete a work in 6 days. It takes 150 days for a single woman to complete the work. In how many days can a single man complete the work?

(SSC CGL Tier-1 2023 (25 Jul · Shift 4 · 5:15 PM))
(SSC CGL Pre 2023)
  1. 450
  2. 225
  3. 350
  4. 210
Answer (Detailed Solution Below)
Option 1 : 450

Detailed Solution

Concept approach

Work = 150 woman-days; 20 women × 6 = 120

⇒ remaining 30 = 15 men × 6 = 90 man-days

⇒ 1 man-day = 1/3 unit

⇒ 150 units = 450 days

⇒ option A

ऐसे ही सवालों के असली परीक्षा जैसे मॉक टेस्ट — मुफ़्तStart free test →