A, B and C can do a work in 12, 15 and 18 days respectively. They started together, but A left after 2 days and B left 3 days before the completion of the work. Find the number of days taken to complete the work.

  1. 8 5/11
  2. 8 3/11
  3. 10 5/11
  4. None of these
Answer (Detailed Solution Below)
Option 1 : 8 5/11

Detailed Solution

Concept approach

Work 180: A = 15, B = 12, C = 10. BC = (180 − 2 × 15 + 3 × 12)/22 = 186/22 = 93/11 = 8 5/11 days