A and B working together can complete a work in d days. Working alone, A takes (8 + d) days and B takes (18 + d) days. A works for 4 days and the remaining work is completed by B alone in:

(SSC CGL 04.03.2020)
  1. 24
  2. 18
  3. 16
  4. 20
Answer (Detailed Solution Below)
Option 1 : 24

Detailed Solution

Concept approach

d = √(8 × 18) = 12

⇒ A = 20, B = 30 days. A in 4 days = 1/5

⇒ B does 4/5 × 30 = 24 days

Ultra Calci trickLCM work + (note) d = √(ab)

(note) 1/(8 + d) + 1/(18 + d) = 1/d

⇒ d² = 8 × 18 = 144

⇒ d = 12

⇒ A = 20, B = 30 days

LCM 60: A = 3, B = 2 per day; A works 4 days = 12

⇒ left 48

48 ÷ 2 = 24 ✓

⇒ 24 days