A contractor employs 15 men to complete a work in 24 days, working 8 hours per day. After six days, he adds five more men but also reduces the working hours to six per day from the seventh day onwards. If all men work with the same efficiency throughout, how many more days will be required to finish the remaining work?

(SSC CGL Tier-1 2025 (20 Sep · Shift 1 · 9:00 AM))
  1. 20
  2. 18
  3. 21
  4. 22
Answer (Detailed Solution Below)
Option 2 : 18

Detailed Solution

Concept approach

Total work = 15 × 24 × 8 = 2880 man-hours. 6 days: 15 × 6 × 8 = 720

⇒ left 2160. Now 20 men × 6 h = 120/day

⇒ 2160/120 = 18 days

Ultra Calci trickman-hours

Work = 15 × 24 × 8 = 2880; 6 days done = 15 × 6 × 8 = 720 → left 2160

20 men × 6 h = 120 per day → 2160/120 = 18 days

⇒ 18