A contractor employs 15 men to complete a work in 24 days, working 8 hours per day. After six days, he adds five more men but also reduces the working hours to six per day from the seventh day onwards. If all men work with the same efficiency throughout, how many more days will be required to finish the remaining work?
(SSC CGL Tier-1 2025 (20 Sep · Shift 1 · 9:00 AM))
- 20
- 18
- 21
- 22
Answer (Detailed Solution Below)
Option 2 : 18
Detailed Solution
Concept approach
Total work = 15 × 24 × 8 = 2880 man-hours. 6 days: 15 × 6 × 8 = 720
⇒ left 2160. Now 20 men × 6 h = 120/day
⇒ 2160/120 = 18 days
Ultra Calci trickman-hours
Work = 15 × 24 × 8 = 2880; 6 days done = 15 × 6 × 8 = 720 → left 2160
20 men × 6 h = 120 per day → 2160/120 = 18 days
⇒ 18
एक ठेकेदार 15 आदमियों को एक काम 24 दिनों में पूरा करने के लिए नियुक्त करता है, जो प्रतिदिन 8 घंटे काम करते हैं। छह दिनों के बाद, वह पाँच और आदमियों को जोड़ता है, लेकिन सातवें दिन से काम के घंटे भी घटाकर प्रतिदिन छह कर देता है। यदि सभी आदमी पूरे समय एक ही दक्षता से काम करते हैं, तो शेष काम को पूरा करने के लिए कितने और दिनों की आवश्यकता होगी?
(SSC CGL Tier-1 2025 (20 Sep · Shift 1 · 9:00 AM))
- 20
- 18
- 21
- 22
उत्तर (विस्तृत हल नीचे)
विकल्प 2 : 18
विस्तृत हल
कॉन्सेप्ट से हल
कुल कार्य = 15 × 24 × 8 = 2880 व्यक्ति-घंटे। 6 दिन: 15 × 6 × 8 = 720
⇒ शेष 2160। अब 20 × 6 = 120/दिन
⇒ 2160/120 = 18 दिन
अल्ट्रा कैलसी ट्रिकman-hours
काम = 15 × 24 × 8 = 2880; 6 दिन में 15 × 6 × 8 = 720 → शेष 2160
20 पुरुष × 6 घंटे = 120 प्रतिदिन → 2160/120 = 18 दिन